Blog · Commercial
Who Approves Your Commercial Build-Out? 5 Questions to Ask Before You Sign
The landlord, the building department, the fire marshal, the utility and the reviews nobody mentions. Five approvals to know about before the signature.
Signing a lease on a space and then discovering that the landlord, the building department, the fire marshal and the utility all have a different opinion about what can go in it is the most expensive way to learn the sequence. Five approvals, five questions, and the answer to each one belongs in the conversation before the signature, not after the first inspection.
1The landlord, and what the lease actually allows
The first approval is not a government one and it is the one with the most teeth, because the landlord can say no to everything and can require you to put the space back the way it was at the end of the term. The lease has an alterations clause, a restoration clause and sometimes a list of prohibited work, and the build-out that ignores it is a build-out that ends with a restoration bill. Ask for the alterations clause in writing, with the list of what needs written consent, and ask whether the plan has to be submitted to the landlord before it goes to the building department, because in most buildings it does.
2The building department, and what gets reviewed
The building department reviews the construction documents and issues the permit, and the permit is the document that lets anybody start. The review is where the accessible route is checked, because the 2010 ADA Standards apply to the space, and where the occupancy and the construction type of the space are read against what the drawings show. A layout that does not match the plan of record does not get a permit, so the drawings that go in are the drawings that get built.
3The fire marshal, and the systems that are not yours to change
The fire marshal has an opinion about the exit routes, the alarm, the sprinklers, the fire separation and the storage, and most of those systems were installed for the building and not for your suite. The requirements are specific: the exit routes have to be free and unobstructed with nothing placed in them, each exit has to be clearly visible and marked with no decoration or sign allowed to obscure the exit door, and the employer has to have and maintain an employee alarm system with a distinctive signal for each purpose. A change to the alarm or the sprinklers is a change to the building.
4The utility, and the service you are going to need
This is the one nobody asks about and the one that moves the schedule most. The electrical service has to be able to carry the load, the meter has to be where the utility will put it, and in a leased space the power may be sub-metered or it may have to be brought in from the building, which is a conversation with the landlord and with the utility and sometimes with both. The rules are not negotiable either: the conductors and the equipment have to be approved, listed equipment has to be installed and used according to its listing, and the completed installation has to be free from recognized hazards.
5The reviews that do not depend on anybody signing anything
Two of them are federal and they arrive whether the landlord agrees or not. The renovation rule for asbestos-containing material sets the notification requirement and the work practices for a renovation or a demolition, and it applies to the work, not to the lease. And if the space has a kitchen, the Food Code plan submission has to carry the intended menu, the anticipated volume of food, the proposed layout, the mechanical schematics, the construction materials and the finish schedules. A layout that changes after that review goes back through the review.
How to sequence the approvals
Two things, and both of them are about the order.
Get the landlord in writing before the drawings are finished
The landlord can kill a layout in a meeting and nobody has spent money yet. Get the alterations approved in writing, get the list of what has to go back to how it was, and get the answer about the utility in the same conversation, because that answer changes the electrical design.
Build a calendar with the reviews on it
Ask each reviewer for the review time and what they need in order to review it, and put those dates on the project calendar next to the demolition date. The reviews are the fixed points of the schedule and everything else moves around them, including the cabinets and the counter.
What to ask before you sign
Two questions, and both of them are about the space.
What was approved here last time
Ask for the as-built drawings of the space and for the permits of the previous tenant, and ask whether anything in them is still active. A suite that was a restaurant and is now an office carries the grease interceptor, the hood and the floor drains of a restaurant, and the question of whether they get capped or stay is a question that has to be answered before the design, not after.
What is excluded from the approvals we have
Ask what is not covered by the permits already in place: the asbestos survey, the fire alarm, the sprinklers, the electrical service and the accessibility review. Every item on that list is a review, a schedule and a document, and knowing the list in advance is the difference between a plan and a hope.
The 5 approvals
| Who approves | What they check | When to ask |
|---|---|---|
| The landlord | The alterations, the restoration, the utility | Before the drawings are finished |
| The building department | The construction documents and the permit | After the landlord, before anybody starts |
| The fire marshal | The exits, the alarm, the sprinklers, the storage | With the plan review, not after it |
| The utility | The service, the meter and the load | Before the electrical design is finished |
| The federal reviews | The asbestos notification, the food establishment plans | Before the demolition starts |
Where this comes from
Six public documents: the rule behind each approval, from the accessible route to the asbestos notification.
- DOJ — 2010 ADA Standards for Accessible Design — the accessible route, the clear width of walking surfaces and the turning space that the plan review checks.
- eCFR — 29 CFR 1910.37, Exit routes — the routes that have to stay free and unobstructed, and the marking and the lighting of every exit.
- eCFR — 29 CFR 1910.38, Emergency action plans — the employee alarm system with a distinctive signal for each purpose, and the minimum elements of the plan.
- eCFR — 29 CFR 1910.303, Electrical, general — that the conductors and the equipment have to be approved, that listed equipment is used per its listing, and that a completed installation is free from recognized hazards.
- eCFR — 40 CFR 61.145, Standard for demolition and renovation — the notification requirement for a renovation or demolition that disturbs asbestos-containing material.
- FDA — Food Code 2022 (8-201.12, the contents of the plans for review) — the contents of the plans submitted for review: the intended menu, the anticipated volume of food, the proposed layout, the mechanical schematics, the construction materials and the finish schedules.
Start with the lease and the alterations clause. It is the only approval that can send the whole project back, and it is the one nobody reads in the room.
We run the same approval sequence on every commercial build-out we do. See our process →
Want the approvals settled before the signature?
We build the sequence, name the reviewer for each item and put the dates on the schedule before the lease is signed.