(901) 334-1320

Blog · Commercial

Commercial Build-Out: 7 Things That Set the Open Date

The inspection before the demolition, the exit routes, the accessible route, the plan for opening day, the electrical, the chemicals and the kitchen. Seven items on the critical path.

Commercial interior under construction with steel stud walls, exposed ducts and a bare concrete floor
Illustration — a commercial interior in the framing stage, with steel studs, exposed ductwork and a bare slab, which is when the layout decisions are still cheap to change.

The open date on a commercial fit-out is decided long before the finishes. It is decided by the things with a rule or a waiting period attached: an inspection before anything comes down, a notice on its way before the work starts, an exit route that cannot be blocked, a corridor that has to be wide enough, and a plan for the people working in the space. Seven of them, all federal. This is what they are and why they sit on the critical path.

1The inspection that has to happen before the demolition

The first item is what has to be known before the demolition. The federal asbestos standard requires that, prior to the commencement of a demolition or renovation, the affected facility or the part where the work will occur be thoroughly inspected for asbestos, including Category I and Category II nonfriable material. It also sets the notice: at least 10 working days before asbestos stripping or removal, or any activity that would break up, dislodge or disturb the material. Ten working days is not paperwork. It is calendar.

2The exit routes, which are decided by the layout

OSHA requires exit routes to be free and unobstructed, and the exit access must not go through a room that can be locked, such as a bathroom, nor lead into a dead-end corridor, with stairs or a ramp where the route is not level. Each route must be adequately lighted, each exit clearly visible and marked with a sign reading Exit, and no sign may obscure the door. Every one of those is a wall position.

3The accessible route, which is also the layout

The same floor plan has to clear the accessibility standards. Under the federal accessibility standards, the clear width of walking surfaces is 36 inches minimum, with a permitted reduction to 32 inches for a short length. The running slope cannot be steeper than 1 in 20, the cross slope cannot be steeper than 1 in 48, and a turning space must be 60 inches in diameter minimum. A corridor one stud too narrow has to be rebuilt.

4The plan for the day the doors open

A commercial space is finished when it can be operated, and the operating plan has its own requirements. The emergency action plan standard requires the minimum elements, including the procedure for reporting a fire or other emergency and the procedure for evacuation, with the exit route assignments. It also requires the employer to have and maintain an employee alarm system, using a distinctive signal for each purpose. That plan is posted once, and it depends on a layout already fixed.

5The electrical, and what is allowed on the site

The power is on the critical path because it cannot be improvised. Under the general electrical requirements, the conductors and equipment are acceptable only if approved, listed or labeled equipment must be installed and used per the instructions in its listing or labeling, and completed wiring installations have to be free from hazards. In a tenant improvement that is a conversation about the panel, the circuits and the equipment on them, and it happens while the walls are still open.

6The chemicals that stay in the building

A fit-out fills a space with products that keep working after the crew leaves: cleaners, adhesives, sealants and paints. The hazard communication standard requires the written program for the workplace, including the lists of hazardous chemicals present, the labeling of containers, safety data sheets and training. That is the handover: a document the operator needs before the first delivery.

7The kitchen, where the schedule is always tightest

The food service area is where a commercial opening date usually slips. The accessibility standards have their own chapter for kitchens, kitchenettes and sinks: where sinks are provided, at least 5 percent, but no fewer than one, of each kind of sink is accessible. EPA notes that local kitchen fans that exhaust outdoors remove contaminants directly from the room where the fan is located. A recirculating hood is not that, and the difference is a duct that has to run through a building that is already closed.

What happens before the first wall goes up

Two pieces of work happen first, and neither is visible in the finish.

The survey of what is already there

Asbestos has to be ruled out before the demolition, and the survey that does it also produces the picture of what the building contains: the walls, the ceiling, the mechanical and the electrical to be de-energized. Everything the schedule is built on comes out of that survey, which is why it cannot be skipped when the date looks tight.

The layout drawn to the rules, not to the drawing

The exit routes, the accessible route and the restroom clearances are dimensions that have to be resolved while the plan is still a plan: 36 inches of clear width, a 60-inch turning space, no locked room on the way to the exit, no dead-end corridor. A layout that ignores them has to be redrawn after the studs go up, which is the most expensive week of the project.

What to ask before the lease is signed

Two questions, and they decide whether the date is real.

What is on the critical path, and what is the calendar

Ask which items have a regulatory waiting period attached, and when each one starts. The asbestos notice alone is ten working days before the work begins, and it cannot start before the inspection is done. Ask for the schedule with those items on it, not around them.

What happens when the inspector finds something

Ask what the process is when something is found that was not in the drawings: who stops, who decides, what the schedule does. The answer should be a procedure, not a favour, and the contractor who has one already is the one whose date holds.

The seven items and what each one requires

The itemWhat the rule requiresThe question that settles it
The asbestos inspectionA thorough inspection before the demolition, and notice at least 10 working days aheadWhen does the inspection happen, and when was the notice sent?
The exit routesFree and unobstructed, no locked rooms on the way out, each exit marked and lightedWhere are the exits, and what is the door schedule?
The accessible route36 inches of clear width, a 60-inch turning space, slopes within 1 in 20 and 1 in 48Is the corridor dimensioned on the plan?
The emergency action planA written plan with the evacuation procedure and exit route assignments, plus the alarmWho writes the plan, and when is it posted?
The electricalApproved equipment only, installed and used per its listing, with insulation integrityIs the panel and the circuit schedule in the documents?
The hazardous chemicalsA written program, the chemical list, labels, safety data sheets and trainingWhat is in the building once the crew leaves?
The kitchenAccessible sinks as required, and a hood that exhausts outdoorsWhere does the hood discharge, and is it ducted or recirculating?

Where this comes from

Seven public documents, every one a rule with a date or a dimension attached.

Start with the asbestos standard. It is the one with a waiting period attached, and everything else schedules around it.

The same sequence runs on every commercial build-out. See our process →

Want the open date worked out before the lease is signed?

We survey what is there, draw the layout against the rules that will be inspected, and put the waiting periods on the schedule.