Blog · Office Build-Out
Office Demolition: 5 Things We Verify Before Anyone Prices From a Floor Plan
Behind the walls, in the paint, in the dust, in the live circuits and in the rated assemblies. Five things that decide the price before the price exists.
Pricing a demolition from a floor plan is guessing with a spreadsheet, and the guess is always wrong in the same direction. There are five things that have to be looked at before the number means anything, and four of them are regulated by federal rules that decide who may do the work, what has to be notified and how long it takes.
1What is behind the walls and above the ceiling
The first thing an office demolition opens is the space nobody planned: the wall cavities, the plenum above the ceiling tiles, the shafts, the old millwork, the partition that was added in a hurry. The asbestos standard for construction work classifies the jobs by type and requires the competent person to identify the asbestos hazards and select the control strategy before the work happens, and the renovation rule for asbestos-containing material sets the notification requirement and the work practices. A plan that does not include that survey is a plan with an unknown in it that is bigger than the demolition.
2The paint on the walls, and the year the building was built
An office fit-out in a building from the seventies means lead-based paint, and the federal rules for it are specific: the certification, the occupant protection and the clearance requirements, and the renovation work practice standards, alongside the HUD rules. The practical consequence is not only the cost of the prep, it is the sequence: the paint has to be tested and the work practices have to be planned before the demolition starts, not discovered in the middle of a corridor.
3The dust, and the containment that goes with it
Demoising an office produces three different dusts and the rules are not the same for all of them. Cutting concrete, tile and masonry puts respirable crystalline silica in the air, and that standard sets a permissible exposure limit calculated as an eight-hour average and defines the regulated area as the place where that limit can be exceeded. The EPA is blunt about the consequence of water and mold in the building, and the containment, the negative air and the cleaning are not optional extras when the material being cut is the material being cut.
4The circuits that are still live
An office floor has circuits that nobody knows the end of: the power to the partition that came out six years ago, the data cable in the plenum, the circuit for the lighting that was replaced twice, the receptacle on the wall that was never used. The electrical rules are not negotiable: approved and listed equipment, installed and used according to the instructions in its listing, with a completed installation free from recognized hazards. Demolition next to a live circuit is a planning question, and the answer belongs in the pre-demolition checklist.
5The rated assemblies and the routes out
The walls that are rated, the corridor that is an exit route, the door that is on the fire plan, the alarm and the strobes that are part of the building and not part of your suite: this is the fifth thing, and it is the one that decides whether the demolition plan is even permitted. The exit routes have to stay free and unobstructed with nothing placed in them and every exit has to be clearly visible and marked, the emergency action plan and the employee alarm system belong to the employer, and the rating on a wall that is being opened is a detail the fire marshal has an opinion about.
How to price a demolition honestly
Two things, and both of them are about what goes in the document.
Put the survey in the scope, not in the exclusions
Ask for the asbestos survey, the lead survey and the review of the building documents to be part of the scope, with what each one triggers written down. A demolition priced with the surveys excluded is a demolition priced with the risk excluded, and the difference between the two numbers is the change order.
Price the containment and the sequence, not the demolition
Ask what has to be done before the work starts: the containment, the negative air, the survey notifications, the protection of the areas that stay in use. And ask what the sequence is when part of the floor stays in operation, because a demolition that has to happen around a business that is still trading is a different job, on a different schedule, with a different crew.
What to ask before the estimate
Two questions, and both of them are about the documents.
What do the building records say is in this space
Ask for the as-built drawings, the fire plan, the sprinkler and the alarm record for the floor, and the previous tenant’s permits. A space that was a laboratory and is now an office carries a ventilation system and a sink that a plan does not show, and the fire plan is the document that tells you what the wall between your suite and the corridor actually is.
What is the plan for the surprises
Ask what the crew does when the wall opens and there is something nobody expected. The answer should name a person, a price basis and a process, because the question is not whether there will be a surprise, it is whether the surprise gets absorbed or passed on.
The 5 verifications
| What is verified | What it changes | The rule behind it |
|---|---|---|
| What is behind the surfaces | The work practices, the notification, the crew | The asbestos standard and the renovation rule |
| The lead paint | The preparation, the sequence, who may do the work | The lead-based paint provisions |
| The dust | The containment and the air monitoring | The respirable crystalline silica limit |
| The live circuits | The lockout and the sequencing of the work | The electrical installation rules |
| The rated assemblies | Whether the demolition plan can be permitted | The exit routes and the emergency action plan |
Where this comes from
Seven public documents: the four regulated verifications and the three that decide what the space is allowed to become.
- eCFR — 29 CFR 1926.1101, Asbestos — the classification of the work by type, the competent person who identifies the asbestos hazards and selects the control strategy, and the training and the waste disposal requirements.
- eCFR — 40 CFR 61.145, Standard for demolition and renovation — the notification requirement for a renovation or demolition that disturbs asbestos-containing material, and the work practices that go with it.
- eCFR — 29 CFR 1910.1053, Respirable crystalline silica — the permissible exposure limit for respirable crystalline silica and the definition of the regulated area where that limit can be exceeded.
- eCFR — 40 CFR 745.65, Lead-based paint poisoning prevention — the certification, occupant protection and clearance requirements, and the renovation work practice standards, alongside the HUD rules at 24 CFR part 35.
- eCFR — 29 CFR 1910.303, Electrical, general — that the conductors and the equipment have to be approved, that listed equipment is used per its listing, and that a completed installation is free from recognized hazards.
- eCFR — 29 CFR 1910.37, Exit routes — the routes that have to stay free and unobstructed, and the marking and the lighting of every exit.
- eCFR — 29 CFR 1910.38, Emergency action plans — the exit route assignments and the employee alarm system with a distinctive signal for each purpose.
Start with the asbestos standard and the renovation rule. They are the two documents that decide what the demolition day is allowed to look like, and they are the ones that turn an estimate into a schedule.
The same verification runs on every office build-out we do. See our process →
Want the demolition price to be the price?
We survey first, we sequence the containment and the notifications, and the number we give you is the number we expect to close at.