Office Demolition: 5 Things We Verify Before Anyone Prices From a Floor Plan

Behind the walls, in the paint, in the dust, in the live circuits and in the rated assemblies. Five things that decide the price before the price exists.

Office being demolished with the carpet stacked and the partition cut to the studs
Illustration — the office stripped back, which is where the price that was quoted on paper turns into the price that has to be paid.

Pricing a demolition from a floor plan is guessing with a spreadsheet, and the guess is always wrong in the same direction. There are five things that have to be looked at before the number means anything, and four of them are regulated by federal rules that decide who may do the work, what has to be notified and how long it takes.

1What is behind the walls and above the ceiling

The first thing an office demolition opens is the space nobody planned: the wall cavities, the plenum above the ceiling tiles, the shafts, the old millwork, the partition that was added in a hurry. The asbestos standard for construction work classifies the jobs by type and requires the competent person to identify the asbestos hazards and select the control strategy before the work happens, and the renovation rule for asbestos-containing material sets the notification requirement and the work practices. A plan that does not include that survey is a plan with an unknown in it that is bigger than the demolition.

2The paint on the walls, and the year the building was built

An office fit-out in a building from the seventies means lead-based paint, and the federal rules for it are specific: the certification, the occupant protection and the clearance requirements, and the renovation work practice standards, alongside the HUD rules. The practical consequence is not only the cost of the prep, it is the sequence: the paint has to be tested and the work practices have to be planned before the demolition starts, not discovered in the middle of a corridor.

3The dust, and the containment that goes with it

Demoising an office produces three different dusts and the rules are not the same for all of them. Cutting concrete, tile and masonry puts respirable crystalline silica in the air, and that standard sets a permissible exposure limit calculated as an eight-hour average and defines the regulated area as the place where that limit can be exceeded. The EPA is blunt about the consequence of water and mold in the building, and the containment, the negative air and the cleaning are not optional extras when the material being cut is the material being cut.

4The circuits that are still live

An office floor has circuits that nobody knows the end of: the power to the partition that came out six years ago, the data cable in the plenum, the circuit for the lighting that was replaced twice, the receptacle on the wall that was never used. The electrical rules are not negotiable: approved and listed equipment, installed and used according to the instructions in its listing, with a completed installation free from recognized hazards. Demolition next to a live circuit is a planning question, and the answer belongs in the pre-demolition checklist.

5The rated assemblies and the routes out

The walls that are rated, the corridor that is an exit route, the door that is on the fire plan, the alarm and the strobes that are part of the building and not part of your suite: this is the fifth thing, and it is the one that decides whether the demolition plan is even permitted. The exit routes have to stay free and unobstructed with nothing placed in them and every exit has to be clearly visible and marked, the emergency action plan and the employee alarm system belong to the employer, and the rating on a wall that is being opened is a detail the fire marshal has an opinion about.

How to price a demolition honestly

Two things, and both of them are about what goes in the document.

Put the survey in the scope, not in the exclusions

Ask for the asbestos survey, the lead survey and the review of the building documents to be part of the scope, with what each one triggers written down. A demolition priced with the surveys excluded is a demolition priced with the risk excluded, and the difference between the two numbers is the change order.

Price the containment and the sequence, not the demolition

Ask what has to be done before the work starts: the containment, the negative air, the survey notifications, the protection of the areas that stay in use. And ask what the sequence is when part of the floor stays in operation, because a demolition that has to happen around a business that is still trading is a different job, on a different schedule, with a different crew.

What to ask before the estimate

Two questions, and both of them are about the documents.

What do the building records say is in this space

Ask for the as-built drawings, the fire plan, the sprinkler and the alarm record for the floor, and the previous tenant’s permits. A space that was a laboratory and is now an office carries a ventilation system and a sink that a plan does not show, and the fire plan is the document that tells you what the wall between your suite and the corridor actually is.

What is the plan for the surprises

Ask what the crew does when the wall opens and there is something nobody expected. The answer should name a person, a price basis and a process, because the question is not whether there will be a surprise, it is whether the surprise gets absorbed or passed on.

The 5 verifications

What is verifiedWhat it changesThe rule behind it
What is behind the surfacesThe work practices, the notification, the crewThe asbestos standard and the renovation rule
The lead paintThe preparation, the sequence, who may do the workThe lead-based paint provisions
The dustThe containment and the air monitoringThe respirable crystalline silica limit
The live circuitsThe lockout and the sequencing of the workThe electrical installation rules
The rated assembliesWhether the demolition plan can be permittedThe exit routes and the emergency action plan

Where this comes from

Seven public documents: the four regulated verifications and the three that decide what the space is allowed to become.

Start with the asbestos standard and the renovation rule. They are the two documents that decide what the demolition day is allowed to look like, and they are the ones that turn an estimate into a schedule.

The same verification runs on every office build-out we do. See our process →

Want the demolition price to be the price?

We survey first, we sequence the containment and the notifications, and the number we give you is the number we expect to close at.